How Much Lead Time Does Pre-Shipment Coating Add?

Key facts

Key facts: How Much Lead Time Does Pre-Shipment Coating Add?
RouteWhat drives the added lead time
Loose coils, dip and oven cureBatch size and line slot
Complete units, masking and air-dry cureAir-dry cure time (PG-C 72 h)
Coil removed, dipped and refittedRemoval, refit and pressure check
First article for a new customer or systemApproval turnaround

What takes the time

  1. Transport from the supplier factory to the coating line and on to the port.
  2. Coating and cure. Oven cure is fast; air-dry systems need days before handling and packing.
  3. QC and packing, including photo records.
  4. First-article approval for a new customer or coating system.

Keeping it off the critical path

Book the coating slot when the equipment is ordered, and time the collection with the factory’s completion date. Approving the first article from photos and thickness records avoids waiting for a site visit.

What this means for your project

Send the equipment list, quantity and factory location with your enquiry; the quote states the added lead time for your route.

Technically reviewed byPelagard Technical TeamCoating selection, application and quality controlLast reviewed:
Request a quote

Tell us the equipment, the site and the destination port. We reply within 24 hours.

WhatsAppRequest a Quote